Project Description:
KINGSTON- TRAFFIC SAFETY IMPROVEMENTS ON ROUTE 3A AT EVERGREEN STREET AND POTTLE STREET
Location:
  • Town of Kingston
  • Resident Engineer: Robert Fitzgerald
    Construction Contract Value: $484,948.49
    Construction Bid Price: $327,888.46
    Initial Construction Estimate: $262,952.00
    District: District 5

    Contracts (1) Progress
    # 34565 -- Construction Contract
    Traffic Safety Improvements on Route 3A at Evergreen & Pottle Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/10/2004
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/20/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Status Advertised 09/27/2003