Project Description: |
NORWOOD- BRIDGE REPLACEMENT, N-25-003, MORSE STREET OVER THE NEPONSET RIVER
The existing Morse Street over the Neponset River bridge will be replaced with a single span prestressed concrete deck beam structure on new stub abutments. A temporary bridge will carry traffic during construction.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | Municipality |
Project Manager: | Gautam Sen |
Estimated Total Contract Cost: | $1,141,354.00 |
Estimated Total Federal Participating Construction Cost: | N/A |
Total Estimated Project Cost: | $600,000.00 |
District: | District 5 |
Current Status: | This project has been advertised for construction bids. (as of 08/15/2009 ) |
|
Bridges
|
|
|
|