HOLDEN- BRIDGE REPLACEMENT, H-18-011, MILL STREET OVER THE QUINAPOXET RIVER
The work under this project consists of replacing the town-owned, structurally-deficient Mill Street bridge over the Quinapoxet River with a new bridge and associated improvements. The existing bridge will be demolished and replaced with a new single span pre-cast sectional concrete rigid frame bridge that is approximately 41 feet long and 24.5 feet wide along with cast-in-place footings, guardrail, reconstruction of the bridge roadway approaches, riprap, and signage.
Location:
  • Town of Holden
  • Resident Engineer: Hassan Valipour
    Construction Contract Value: $1,325,553.00
    Construction Bid Price: $1,095,521.75
    Initial Construction Estimate: $1,280,710.40
    District: District 3

    Contracts (1) Progress
    # 56294 -- Construction Contract
    Holden - Bridge Replacement (H-18-011) Mill Street over Quinapoxet River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/14/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/19/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 11/26/2001
    Project Status Advertised 06/21/2008
    Project Status Advertised 06/28/2008
    Project Management
    100% Design 100% Package Received 09/30/2002
    100% Design 100% Package Comments to DE 03/20/2007
    25% Design 25% Package Received 12/30/2001
    25% Design Design Public Hearing 05/30/2002
    75% Design 75% Package Received 08/30/2002
    Final Design PS&E Received 02/16/2007
    Final Design PS&E to FAPRO 12/14/2007