Project Description:
FITCHBURG- LEOMINSTER- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE 2
This project consists of resurfacing and related work (drainage cleaning, guardrail replacement, sign replacement, drainage system cleaning and repairs, tree and brush removal along shoulders) on Route 2 from approximately Mt. Elam Road westerly 1.9 miles to the vicinity of the Route 31 interchange. Construction of a deceleration lane at Palmer Road (eastbound) is included.
Location:
  • City of Fitchburg
  • City of Leominster
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Albert Li
    Estimated Total Contract Cost: $2,034,600.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project