Project Description:
BILLERICA- BRIDGE REPLACEMENT, BR# B-12-001, ROUTE 4 (NASHUA ROAD) OVER CONCORD RIVER
The work consists of replacing the existing bridge and improving 200 adjacent meters of Route 4. The work will also include partial removal of the existing abutments, removal of the existing piers, and construction of new abutments and piers. Two lanes of traffic will be maintained during construction.
Location:
  • Town of Billerica
  • Resident Engineer: Charles Sabella
    Construction Contract Value: $4,955,265.00
    Construction Bid Price: $4,468,787.00
    Initial Construction Estimate: $3,457,450.00
    District: District 4
    Current Status: Project is Complete. Minor punch list items pending. (as of 01/12/2009)
    Additional Info: Completion date for this project is May 29, 2009. (as of 01/12/2009)

    Contracts (3) Progress
    # 30279 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 45142 -- Construction Contract
    Billerica - Bridge Replacement (B-12-001) (Steel) - Route 4 (Nashua Rd) over the concord River Completed
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 07/14/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project is Complete. Minor punch list items pending.
    Additional Info
    Completion date for this project is May 29, 2009.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/27/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 10/31/2001
    Project Status Advertised 09/24/2005
    Project Management
    100% Design 100% Package Received 04/06/2005
    100% Design 100% Package Comments to DE 05/16/2005
    25% Design 25% Package Received 08/30/2002
    25% Design 25% Package Comments to DE 06/13/2003
    25% Design Design Public Hearing 09/09/2003
    75% Design 75% Package Received 11/25/2003
    75% Design 75% Package Comments to DE 02/18/2005
    Final Design PS&E Received 06/22/2005
    Final Design PS&E to FAPRO 06/22/2005
    Consultant Contract Process Scope to DE 07/30/2001
    Consultant Contract Process NTP Issued 10/30/2001