BARNSTABLE- RESURFACING AND RELATED WORK ON ROUTE 6 FROM SANDWICH/BARNSTABLE T.L. TO BARNSTABLE/YARMOUTH T.L. (13,630 METERS)
The work under this contract consists of clearing and thinning, coldplaning, guardrail, and resurfacing with on Route 6 and all ramps from the Sandwich/Barnstable Town Line to the Barnstable/Yarmouth Town Line. Length of project = 44,717 Feet.
Location:
  • Town of Barnstable
  • Resident Engineer: Paul Burns
    Construction Contract Value: $4,448,471.67
    Construction Bid Price: $3,498,821.25
    Initial Construction Estimate: $4,072,395.00
    District: District 5

    Contracts (1) Progress
    # 34509 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 6. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/29/2004
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/27/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 10/31/2001
    Project Status Advertised 09/13/2003