Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- BRIDGE REPLACEMENT, B-16-167, RIVER STREET OVER MBTA
The purpose of this project is to replace the existing structurally deficient bridge carrying River Street over the MBTA railroad tracks with a new shorter bridge (29 feet). The new bridge will be constructed using accelerated construction techniques. Without disturbing traffic, new abutments will be constructed under the bridge while the new bridge structure will be pre-built adjacent to the bridge site. The road will be closed for 10 days while the old bridge is removed and the new bridge will be lifted into place in one piece. The new bridge will provide a wider roadway (39+ feet curb to curb), and two 6.5 feet sidewalks.
Location:
  • City of Boston
  • Resident Engineer: Fritz Dubuisson
    Construction Contract Value: $7,928,740.00
    Construction Bid Price: $5,732,157.00
    Initial Construction Estimate: $7,917,638.25
    District: District 6

    Contracts (4) Progress
    # 30286 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 57462 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 59589 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 67664 -- Construction Contract
    Bridge Replacement and Related Work (B-16-167) (Steel) – River Street over the MBTA Railroad. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/03/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/01/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 10/31/2001
    Project Status Advertised 09/18/2010
    Project Management
    25% Design 25% Package Received 12/17/2007
    25% Design 25% Package Received 09/17/2009
    25% Design 25% Package Comments to DE 10/16/2008
    25% Design 25% Package Comments to DE 10/16/2008
    25% Design 25% Package Comments to DE 10/16/2008
    25% Design 25% Package Comments to DE 10/16/2008
    25% Design 25% Package Comments to DE 03/13/2009
    25% Design 25% Package Comments to DE 10/26/2009
    25% Design Design Public Hearing 06/30/2004
    25% Design Design Public Hearing 06/26/2008
    25% Design Design Public Hearing 10/08/2009
    75% Design 75% Package Received 04/06/2010
    75% Design 75% Package Comments to DE 07/01/2010
    Final Design PS&E Received 08/06/2010
    Final Design PS&E to FAPRO 08/18/2010
    Consultant Contract Process Scope to DE 10/27/2006
    Consultant Contract Process NTP Issued 04/06/2007