WESTFIELD- ROUTE 20 ACCESS IMPROVEMENTS ON COURT STREET & WESTERN AVENUE, FROM LLEWELLYN DRIVE EASTERLY TO LLOYDS HILL ROAD (PHASE I)
This reconstruction project on city-owned streets begins on Western Avenue at Llewellyn Drive 2.0 miles easterly to Lloyds Hill Road. The project will include left-turn lane construction at Lloyd's Hill and sidewalks, crosswalks and pavement markings.
Location:
  • City of Westfield
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Victoria Hayes
    Construction Bid Price: $6,847,972.50
    District: District 2

    Contracts (1) Progress
    # 105482 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along Western Avenue (Route 20), Lloyds Hill Road, Broadway and Adjacent Streets (Phase I) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/06/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/04/2001
    Project Review Committee PRC Tabled 06/26/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Status Advertised 08/11/2018
    Project Management
    100% Design 100% Package Received 03/20/2018
    100% Design 100% Package Comments to DE 04/26/2018
    25% Design 25% Package Received 11/04/2014
    25% Design 25% Package Received 04/01/2016
    25% Design 25% Package Comments to DE 06/09/2016
    25% Design Design Public Hearing 01/31/2017
    75% Design 75% Package Received 06/12/2017
    75% Design 75% Package Comments to DE 08/11/2017
    Final Design PS&E Received 06/28/2018
    Final Design PS&E Received - Resub 1 07/23/2018