| Project Description: |
WESTFIELD- ROUTE 20 ACCESS IMPROVEMENTS ON COURT STREET & WESTERN AVENUE, FROM LLEWELLYN DRIVE EASTERLY TO LLOYDS HILL ROAD (PHASE I)
This reconstruction project on city-owned streets begins on Western Avenue at Llewellyn Drive 2.0 miles easterly to Lloyds Hill Road. The project will include left-turn lane construction at Lloyd's Hill and sidewalks, crosswalks and pavement markings.
|
| Location: |
|
| Design Responsibility: | Municipality |
| Right of Way Responsibility: | Municipality |
| Project Manager: | Brian Chapman![]() |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 2 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges |
||||||
|
|
|
||