Project Description:
WEST BRIDGEWATER- INTERSECTION IMPROVEMENTS AT ROUTE 106 & ROUTE 28 (CENTRAL SQUARE)
This project consists of intersection improvements at the intersection of state owned Route 28 and town owned Route 106 to address congestion issues in West Bridgewater's downtown area. The Town is interested in including streetscape improvements to their downtown.
Location:
  • Town of West Bridgewater
  • Resident Engineer: Russell Davis
    Construction Contract Value: $2,828,544.00
    Construction Bid Price: $2,326,435.14
    Initial Construction Estimate: $2,307,617.60
    District: District 5

    Contracts (6) Progress
    # 51301 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 55034 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68939 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 79509 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Traffic Signals) at the Intersction of Routes 106 (East and West Center Street) and 28 (North and South Main Streets). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: HIGH PRIORITY PROJECTS
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/18/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 10/19/2001
    Project Status Advertised 08/31/2013
    Project Management
    100% Design 100% Package Received 08/02/2012
    100% Design 100% Package Comments to DE 01/18/2013
    25% Design 25% Package Received 08/12/2009
    25% Design 25% Package Comments to DE 11/01/2010
    25% Design Design Public Hearing 01/27/2011
    75% Design 75% Package Received 11/12/2011
    75% Design 75% Package Comments to DE 05/18/2012
    Final Design PS&E Received 06/13/2013
    Final Design PS&E to FAPRO 08/28/2013
    Consultant Contract Process NTP Issued 03/16/2009
    Consultant Contract Process Workhours Approved 03/16/2009