WEST TISBURY- INTERSECTION IMPROVEMENTS AT STATE ROAD (VINEYARD HAVEN ROAD) AND OLD COUNTY ROAD
Work on this project includes geometric improvements at the intersection of State Road and Old County Road.
Location:
  • Town of West Tisbury
  • Resident Engineer: Richard McKenzie
    Construction Contract Value: $391,579.00
    Construction Bid Price: $339,286.00
    Initial Construction Estimate: $264,943.50
    District: District 5

    Contracts (1) Progress
    # 83034 -- Construction Contract
    Intersection Reconstruction and Related Work at State (Vineyard Haven) and Old County Roads. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/22/2014
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/18/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 02/28/2006
    Project Status Advertised 06/21/2014
    Project Management
    100% Design 100% Package Received 02/18/2014
    100% Design 100% Package Comments to DE 04/03/2014
    100% Design 100% Package Comments to DE 05/05/2014
    100% Design 100% Package Comments to DE 05/14/2014
    25% Design 25% Package Received 07/23/2013
    25% Design 25% Package Comments to DE 10/24/2013
    25% Design Design Public Hearing 11/13/2013
    75% Design 75% Package Received 02/18/2014
    75% Design 75% Package Comments to DE 05/05/2014
    Final Design PS&E Received 05/16/2014
    Final Design PS&E to FAPRO 06/10/2013