Project Description:
DUXBURY- INTERSECTION IMPROVEMENTS @ KINGSTOWN WAY (ROUTE 53) & WINTER STREET
This project will enhance safety and improve the efficiency of the traffic flow by installing a roundabout at the intersection of Kingston Way (Route 53) and Winter Street in the Town of Duxbury.
Location:
  • Town of Duxbury
  • Resident Engineer: Christopher Sera
    Construction Contract Value: $1,393,947.00
    Construction Bid Price: $1,229,799.00
    Initial Construction Estimate: $1,107,172.50
    District: District 5

    Contracts (5) Progress
    # 51304 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 81582 -- Construction Contract
    Construction of a Roundabout and Related Work at Route 53 (Kingston Way and Winter Street). Completed
    # 99081 -- Design -- Traffic Open End
    Statewide - Assist Traffic Engineering with Traffic Control Device Improvement Projects Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/12/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 10/19/2001
    Project Status Advertised 03/29/2014
    Project Management
    100% Design 100% Package Received 03/29/2012
    100% Design 100% Package Comments to DE 02/14/2013
    25% Design 25% Package Received 03/06/2009
    25% Design 25% Package Comments to DE 06/24/2009
    25% Design Design Public Hearing 09/29/2009
    75% Design 75% Package Received 04/05/2010
    75% Design 75% Package Comments to DE 04/22/2011
    Final Design PS&E Received 10/24/2013
    Final Design PS&E to Peer Reviewer 05/22/2013
    Final Design Peer Review Comments to DE 06/28/2013
    Final Design PS&E to FAPRO 03/19/2014
    Consultant Contract Process Scope to DE 09/11/2008
    Consultant Contract Process NTP Issued 10/24/2008