PLYMOUTH- INTERSECTION IMPROVEMENTS @ ROUTE 3A, MANOMET POINT ROAD, STRAND AVENUE
This project will improve the safety and the efficiency of the traffic flow by installing a new traffic signal at the intersection of Route 3A at Manomet Point Road and Strand Avenue in Plymouth. The new signals will include push-button activated pedestrian signals, crosswalks and wheelchair ramps. There will be some minor widening at the intersection to accommodate exclusive turning lanes and Strand Avenue will be realigned to improve the geometry. Driveways at this intersection may also be modified to improve traffic safety.
Location:
  • Town of Plymouth
  • Resident Engineer: Daniel Mastrangelo
    Construction Contract Value: $1,213,486.84
    Construction Bid Price: $943,638.52
    Initial Construction Estimate: $1,099,410.00
    District: District 5

    Contracts (5) Progress
    # 51304 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64304 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 69160 -- Construction Contract
    Intersection Improvements and Related Work on Route 3A (State Road) at Manomet Point Road. Completed
    # 99081 -- Design -- Traffic Open End
    Statewide - Assist Traffic Engineering with Traffic Control Device Improvement Projects Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/30/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/21/2004
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 02/11/2002
    Project Status Advertised 05/28/2011
    Project Management
    100% Design 100% Package Received 01/11/2011
    100% Design 100% Package Comments to DE 03/23/2011
    25% Design 25% Package Received 03/16/2009
    25% Design 25% Package Comments to DE 07/27/2009
    25% Design Design Public Hearing 11/18/2009
    75% Design 75% Package Received 05/04/2010
    75% Design 75% Package Comments to DE 10/26/2010
    Final Design PS&E Received 05/06/2011
    Final Design PS&E to FAPRO 05/25/2011
    Consultant Contract Process Scope to DE 09/11/2008
    Consultant Contract Process NTP Issued 12/05/2008