Project Description:
DUDLEY- WEBSTER- BRIDGE REPLACEMENT, D-12-001=W-12-009, PERRYVILLE ROAD OVER THE FRENCH RIVER
The project includes the demolition of the existing bridge located on Perryville Road over the French River and the construction of a new single span bridge. The length of the new bridge will increase to 26.00 meters and the width will increase to 10.59 meters. The proposed project length is approximately 110 meters and includes roadway reconstruction at the approaches, new pavement markings, drainage improvements, highway guard installation, and overhead utility relocation.
Location:
  • Town of Dudley
  • Town of Webster
  • Resident Engineer: David Windoloski
    Construction Contract Value: $1,585,447.00
    Construction Bid Price: $1,424,952.70
    Initial Construction Estimate: $1,746,000.00
    District: District 3

    Contracts (4) Progress
    # 30273 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 51303 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 58213 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 65956 -- Construction Contract
    Bridge Replacement (D-12-001=W-12-009) (Concrete) – Perryville Road over the French River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/29/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/25/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Review Committee Letter 11/30/2001
    Project Status Initiated 06/28/2001
    Project Status Advertised 09/13/2008
    Project Status Advertised 07/03/2010
    Project Management
    100% Design 100% Package Received 05/05/2006
    100% Design 100% Package Received 10/05/2006
    100% Design 100% Package Received 03/06/2007
    100% Design 100% Package Received 07/18/2008
    100% Design 100% Package Comments to DE 07/25/2006
    100% Design 100% Package Comments to DE 01/12/2007
    25% Design 25% Package Received 11/07/2003
    25% Design 25% Package Comments to DE 08/16/2004
    25% Design Design Public Hearing 04/01/2004
    75% Design 75% Package Received 01/24/2006
    75% Design 75% Package Comments to DE 03/08/2006
    Final Design PS&E Received 05/14/2010
    Final Design PS&E to FAPRO 06/29/2010