Project Description: |
LAWRENCE- HIGHWAY RECONSTRUCTION, ROUTE 28 (BROADWAY) BETWEEN CANAL STREET & CEDAR STREET (MALDEN MILLS - PHASE III)
The work under this contract consists of the reconstruction of Route 28 (Broadway) from Canal Street/Water Street to approximately 38 meters north of Green Street, Park Street. Reconstruction is also included from Route 28 to Spruce Street and the Baker Street/Manchester Street/May Street intersection.
|
Location: |
|
Resident Engineer: | Ted Gibson |
Construction Contract Value: | $5,859,163.21 |
Construction Bid Price: | $4,086,110.05 |
Initial Construction Estimate: | $3,983,000.00 |
District: | District 4 |
Current Status: | Concrete sidewalks were placed in Quad 4. Sidewalks in Quad #3 are 90% complete. A leveling course has been installed between School St. and Chestnut St. (as of 10/09/2008) |
|
Bridges |
|
|
|
|