SOUTHWICK- INTERSECTION IMPROVEMENTS AT FOUR LOCATIONS ON ROUTE 57 (FEEDING HILLS ROAD)
The project involves paving, sidewalk replacement left turn lanes and signal equipment at three intersections along Route 57 between Powder Mill Road and Hudson Drive. Also included will be new left turn lanes and signal equipment at the North Longyard Road/Foster Road/Feeding Hills Road intersection.
Location:
  • Town of Southwick
  • Construction Begins: Autumn 2016
    Resident Engineer: Hannah Lapointe
    Construction Bid Price: $3,710,992.25
    District: District 2

    Contracts (1) Progress
    # 96616 -- Construction Contract
    Intersection Improvements at 4 Locations along a Section of Route 57 (Feeding Hills Road). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/16/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/13/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Review Committee Letter 11/30/2001
    Project Status Advertised 07/30/2016
    Project Management
    100% Design 100% Package Received 10/27/2015
    100% Design 100% Package Received 01/07/2016
    100% Design 100% Package Comments to DE 11/30/2015
    25% Design 25% Package Received 02/24/2014
    25% Design 25% Package Comments to DE 12/12/2014
    25% Design Design Public Hearing 04/15/2015
    75% Design 75% Package Received 06/05/2015
    75% Design 75% Package Comments to DE 10/22/2015
    Final Design PS&E Received 03/07/2016
    Final Design PS&E to Peer Reviewer 03/07/2016
    Final Design Peer Review Comments to DE 03/25/2016
    Final Design PS&E to FAPRO 07/21/2016