Project Description:
PRINCETON- HIGHWAY RECONSTRUCTION, BROOK STATION ROAD/BOYLSTON AVENUE (FROM ROUTE 62 TO RUTLAND T.L.)
The project consists of the reconstruction of Brooks Station Road from the Rutland Town Line to the intersection of Conner Lane, and Boylston Avenue from Conner Lane to the intersection of Hubbardston Road (Route 62) and Worcester Road (Route 31) in the Town of Princeton, for a distance of approximately 3.44 miles. The work includes full-depth pavement widening, new cement concrete walk, existing pavement reclamation, replacement of an existing culvert, minor geometric improvements, pavement overlay, new steel beam highway guard, new signs, new pavement markings and other incidental items of work.
Location:
  • Town of Princeton
  • Resident Engineer: Michael Healy
    Construction Contract Value: $2,799,823.00
    Construction Bid Price: $2,422,475.85
    Initial Construction Estimate: $2,009,453.00
    District: District 3

    Contracts (1) Progress
    # 48000 -- Construction Contract
    Princeton - Roadway Reconstruction & Related Work on Sections of Brook Station Road & Boylston Avenue Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/24/2006
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/19/2001
    Project Review Committee PRC Tabled 06/26/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Review Committee Letter 04/03/2002
    Project Status Advertised 09/17/2005
    Project Management
    100% Design 100% Package Received 07/13/2005
    100% Design 100% Package Received 10/25/2005
    100% Design 100% Package Received 12/22/2005
    100% Design 100% Package Received 02/15/2006
    100% Design 100% Package Comments to DE 08/19/2005
    100% Design 100% Package Comments to DE 12/09/2005
    100% Design 100% Package Comments to DE 02/01/2006
    25% Design 25% Package Received 04/27/2004
    25% Design 25% Package Comments to DE 09/02/2004
    25% Design Design Public Hearing 09/29/2004
    25% Design 25% Plans Complete 11/16/2004
    75% Design 75% Package Received 01/18/2005
    75% Design 75% Package Comments to DE 05/20/2005
    75% Design 75% Plans Complete 05/17/2005
    Final Design PS&E Received 10/25/2005
    Final Design PS&E Received 02/15/2006
    Final Design PS&E to FAPRO 09/02/2005