Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WORCESTER- RESURFACING AND RELATED WORK ON SHREWSBURY STREET FROM WASHINGTON SQUARE ROTARY TO ROUTE 9 (BELMONT STREET)
This project consists of the reconstruction of Shrewsbury Street. The project begins at the intersection with Brackett Court and extends northeasterly, a distance of approximately 1.2 miles, to the intersection of Atchinson Street, just west of Route 9. The proposed improvements include geometric modifications to the existing median, pedestrian safety improvements and streetscape enhancements. The roadway will be excavated by cold planer and resurfaced. The sidewalks will be expanded at the intersections with pedestrian neck downs and the on-street parking will be formally delineated.
Location:
  • City of Worcester
  • Resident Engineer: Angela Padavano
    Construction Contract Value: $3,033,925.00
    Construction Bid Price: $2,717,170.00
    Initial Construction Estimate: $2,590,907.50
    District: District 3
    Current Status: Project is complete except for general cleanup. (as of 12/28/2004)

    Contracts (1) Progress
    # 33271 -- Construction Contract
    Resurfacing and Related work on Shrewsbury Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/08/2003
    Contract Information
    Project Designer: Municipality
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project is complete except for general cleanup.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/23/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 11/26/2001
    Project Status Advertised 07/27/2002
    Project Management