Project Description:
BROOKFIELD- RESURFACING AND RELATED WORK ON ROUTE 148 (FISKDALE ROAD), FROM MOLASSES HILL ROAD TO STURBRIDGE T.L.
The project consists of roadway resurfacing of Route 148 (Fiskdale Road) for a length of approximately 2.3 miles. The project will include sight distance improvements at the intersection of Webber Road and Route 148.
Location:
  • Town of Brookfield
  • Construction Begins: Spring 2016
    Resident Engineer: Stanley Choinski
    Construction Bid Price: $1,516,598.91
    District: District 3

    Contracts (1) Progress
    # 91853 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 148 (Fiskdale Road). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/29/2016
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/11/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 08/13/2001
    Project Status Advertised 11/21/2015
    Project Management
    100% Design 100% Package Received 05/18/2015
    100% Design 100% Package Comments to DE 05/22/2015
    25% Design 25% Package Received 02/13/2015
    25% Design 25% Package Comments to DE 03/13/2015
    75% Design 75% Package Received 01/21/2015
    75% Design 75% Package Received 02/13/2015
    Final Design PS&E Received 05/18/2015
    Final Design PS&E Received 06/15/2015
    Final Design Peer Review Comments to DE 05/22/2015
    Final Design PS&E to FAPRO 11/18/2015