| Project Description: |
CLINTON- BRIDGE REPLACEMENT, C-16-002, WATER STREET OVER THE NASHUA RIVER
The proposed work under this project consists of bridge reconstruction, widening, guardrail installation and all other work on Water Street from its intersection with Bolton Street and Harris Street to approximately 30 feet westerly of the Nashua River.
|
| Location: |
|
| Project Manager: | Shawn Holland![]() |
| Estimated Total Contract Cost: | $2,971,790.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 3 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
||||||
|
|
|
||