Project Description:
CLINTON- BRIDGE REPLACEMENT, C-16-002, WATER STREET OVER THE NASHUA RIVER
The proposed work under this project consists of bridge reconstruction, widening, guardrail installation and all other work on Water Street from its intersection with Bolton Street and Harris Street to approximately 30 feet westerly of the Nashua River.
Location:
  • Town of Clinton
  • Resident Engineer: Hassan Valipour
    Construction Contract Value: $2,971,790.00
    Construction Bid Price: $2,689,173.20
    Initial Construction Estimate: $2,979,935.75
    District: District 3

    Contracts (1) Progress
    # 59676 -- Construction Contract
    Bridge Replacement (C-16-002) (Concrete) - Water Wtreet over the Nashua River. (ARRA Project) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 09/10/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/27/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Review Committee PRC Approved 06/08/2006
    Project Review Committee Letter 11/30/2001
    Project Status Advertised 07/25/2009
    Project Management
    100% Design 100% Package Received 02/23/2009
    100% Design 100% Package Comments to DE 04/06/2009
    25% Design 25% Package Received 08/29/2002
    25% Design 25% Package Comments to DE 03/26/2003
    25% Design Design Public Hearing 03/13/2008
    75% Design 75% Package Received 10/24/2007
    75% Design 75% Package Comments to DE 01/30/2008
    Final Design PS&E Received 05/08/2009
    Final Design PS&E to FAPRO 07/10/2009
    Consultant Contract Process Scope to DE 12/18/2001
    Consultant Contract Process NTP Issued 04/01/2002