Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
FALMOUTH- BRIDGE REPLACEMENT, F-03-009, CHAPOQUOIT ROAD OVER WEST FALMOUTH HARBOR
The proposed project consists of replacing the existing four-span structurally deficient steel girder bridge with a new four-span prestressed concrete beam bridge on the same general alignment. The work will extend approximately 300 feet west of the bridge and 400 feet east of the bridge. This approach roadway work will consist of reconstruction of the existing pavement, minor vertical and horizontal alignment improvements, safety improvements for proper guardrail transition to the bridge, pavement markings, and signage. The project will be constructed in two phases of construction using a temporary traffic signal to allow for alternating one-way traffic. A sidewalk will remain open at all times during construction.
Location:
  • Town of Falmouth
  • Resident Engineer: Richard McKenzie
    Construction Contract Value: $3,038,342.00
    Construction Bid Price: $2,667,947.50
    Initial Construction Estimate: $2,953,519.00
    District: District 5

    Contracts (2) Progress
    # 57728 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 60370 -- Construction Contract
    Bridge Replacement (F-03-009) (Concrete) - Chapoquoit Road over West Falmouth Habor. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/08/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/03/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Review Committee Letter 11/30/2001
    Project Status Advertised 09/05/2009
    Project Management
    100% Design 100% Package Received 07/10/2009
    100% Design 100% Package Received 08/06/2009
    100% Design 100% Package Comments to DE 08/20/2009
    25% Design 25% Package Received 08/28/2002
    25% Design 25% Package Comments to DE 11/04/2002
    25% Design Design Public Hearing 06/25/2003
    25% Design Design Public Hearing 10/29/2008
    75% Design 75% Package Received 02/24/2009
    75% Design 75% Package Comments to DE 06/01/2009
    Final Design PS&E Received 08/26/2009
    Final Design PS&E to FAPRO 08/26/2009
    Consultant Contract Process Scope to DE 10/19/2005
    Consultant Contract Process NTP Issued 07/30/2001
    Consultant Contract Process Workhours Approved 02/07/2008