LITTLETON- BRIDGE REPLACEMENT, BR# L-13-016, TAYLOR STREET OVER ROUTE 2
The existing bridge will be replaced with a new two span bridge. The bridge will be constructed in multiple stages in order to maintain two lanes of traffic plus pedestrian access. All construction activities will be done within the State Layout Line.
Location:
  • Town of Littleton
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $4,280,101.00
    Construction Bid Price: $3,792,274.00
    Initial Construction Estimate: $4,007,954.00
    Total Estimated Project Cost: $4,000,000.00
    District: District 3
    Current Status: Project is complete except for minor punch list items. All lanes are open. (as of 10/04/2006)

    Contracts (1) Progress
    # 35842 -- Construction Contract
    Bridge Replacement (L-13-16) Taylor Street over Route (2) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/09/2004
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project is complete except for minor punch list items. All lanes are open.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/13/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Review Committee Letter 11/30/2001
    Project Status Advertised 07/10/2004
    Project Management
    100% Design 100% Package Received 03/16/2004
    100% Design 100% Package Comments to DE 05/07/2004
    25% Design 25% Package Received 05/17/2002
    25% Design 25% Package Comments to DE 07/08/2002
    25% Design Design Public Hearing 06/25/2003
    75% Design 75% Package Received 09/17/2003
    75% Design 75% Package Comments to DE 11/14/2003
    Final Design PS&E Received 06/04/2004
    Final Design PS&E to FAPRO 06/04/2004