Project Description:
HOLDEN- BRIDGE REHABILITATION, H-18-022, PRINCETON STREET OVER QUINAPOXET RESERVOIR
MassHighway is proposing to rehabilitate the town-owned Princeton Street Bridge, which crosses over an outlet from the Quinapoxet Reservoir to the Quinapoxet River. The existing bridge's concrete abutments and corrugated iron arch will be repaired, and a protective coating will be applied to the exposed surface of the arch. A new concrete slab bridge deck will be constructed and will include a decorative bridge rail. New façade elements of the bridge and rail will be faced with stone to match the existing stone facing of the bridge.
Location:
  • Town of Holden
  • Resident Engineer: Lisa Spezzaferro-Pelleti
    Construction Contract Value: $725,772.00
    Construction Bid Price: $627,702.00
    Initial Construction Estimate: $656,103.00
    District: District 3

    Contracts (1) Progress
    # 52897 -- Construction Contract
    Holden - Prineceton Street Bridge over the Quinapoxet Reservior Outlet to Quinapoxet River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/11/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/21/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Review Committee Letter 11/30/2001
    Project Status Advertised 09/16/2006
    Project Management
    100% Design 100% Package Received 08/08/2005
    100% Design 100% Package Comments to DE 06/08/2006
    25% Design 25% Package Received 05/29/2003
    25% Design Design Public Hearing 09/30/2003
    75% Design 75% Package Received 12/09/2003
    75% Design 75% Package Comments to DE 02/17/2004
    Final Design PS&E Received 08/02/2006
    Final Design PS&E to FAPRO 08/02/2006