Project Description:
MARLBOROUGH- BRIDGE REPLACEMENTS, M-06-003, ROBIN HILL STREET OVER ASSABET RIVER & M-06-004, BOUNDARY STREET OVER ASSABET RIVER
This project will result in the replacement of the Robin Hill Road and Boundary Street bridges with single span concrete bridges. The proposed curb-to-curb width on both bridges is 26 feet. Also proposed is the installation of 5 foot wide sidewalks on both bridges and roadway approach work consisting of full depth roadway reconstruction.
Location:
  • City of Marlborough
  • Resident Engineer: Arvind Patel
    Construction Contract Value: $2,941,408.00
    Construction Bid Price: $2,641,443.70
    Initial Construction Estimate: $3,187,879.00
    District: District 3

    Contracts (3) Progress
    # 31218 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 2 Final
    # 55039 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 58134 -- Construction Contract
    2 Bridge Replacments (Concrete) - (M-06-003) Robin Hill Street and (M-06-004) Boundary Street both over Assebet River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/02/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/23/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Status Advertised 12/13/2008
    Project Management
    100% Design 100% Package Received 07/16/2008
    100% Design 100% Package Comments to DE 09/15/2008
    25% Design 25% Package Received 07/18/2002
    25% Design 25% Package Comments to DE 03/31/2003
    25% Design Design Public Hearing 10/14/2003
    75% Design 75% Package Received 05/12/2004
    75% Design 75% Package Received 11/17/2005
    75% Design 75% Package Comments to DE 06/29/2005
    75% Design 75% Package Comments to DE 04/03/2006
    Final Design PS&E Received 09/30/2008
    Final Design PS&E to FAPRO 10/20/2008
    Consultant Contract Process Scope to DE 10/23/2001
    Consultant Contract Process NTP Issued 02/01/2002
    Consultant Contract Process Workhours Approved 01/24/2002