GRAFTON- BRIDGE REPLACEMENT, G-08-007, PLEASANT STREET OVER BLACKSTONE RIVER
The new bridge will be built beside the existing bridge. The existing brige will remain open during construction. All work is being done behind existing retaining walls to minimize environmental impacts.
Location:
  • Town of Grafton
  • Resident Engineer: Kevin Troy
    Construction Contract Value: $1,952,294.00
    Construction Bid Price: $1,744,631.00
    Initial Construction Estimate: $991,555.25
    District: District 3
    Current Status: Progress is continuing on the placement of a temporary utility support system and the anticipated temporary relocation of a gas main. The bridge is closed during construction (as of 07/27/2006)

    Contracts (1) Progress
    # 38359 -- Construction Contract
    Grafton - Bridge Replacement (G-8-7) Pleasant Street over the Blackstone River Terminated

    Bridges

    Contract Dates
    Notice to Proceed: 05/03/2005
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Progress is continuing on the placement of a temporary utility support system and the anticipated temporary relocation of a gas main. The bridge is closed during construction
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/13/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Review Committee Letter 11/30/2001
    Project Status Advertised 06/19/2004
    Project Management
    100% Design 100% Package Received 01/27/2003
    25% Design 25% Package Received 11/26/2001
    25% Design 25% Package Comments to DE 01/15/2002
    25% Design Design Public Hearing 02/07/2002
    75% Design 75% Package Received 04/18/2002
    75% Design 75% Package Comments to DE 11/01/2002
    Final Design PS&E Received 04/13/2004
    Final Design PS&E to FAPRO 06/01/2004