Project Description: |
GRAFTON- BRIDGE REPLACEMENT, G-08-007, PLEASANT STREET OVER BLACKSTONE RIVER
The new bridge will be built beside the existing bridge. The existing brige will remain open during construction. All work is being done behind existing retaining walls to minimize environmental impacts.
|
Location: |
|
Resident Engineer: | Kevin Troy |
Construction Contract Value: | $1,952,294.00 |
Construction Bid Price: | $1,744,631.00 |
Initial Construction Estimate: | $991,555.25 |
District: | District 3 |
Current Status: | Progress is continuing on the placement of a temporary utility support system and the anticipated temporary relocation of a gas main. The bridge is closed during construction (as of 07/27/2006) |
|