Project Description:
FALMOUTH- CONSTRUCTION OF THE SHINING SEA BIKEWAY FROM SKATING LANE TO CARLSON LANE (3,500 FEET) PHASE IIB
This project will result in the construction of a bicycle trail along approximately 1000 meters of abandoned rail line from Skating Lane to Carlson Lane in Falmouth. Landscaping and parking will also be provided.
Location:
  • Town of Falmouth
  • Resident Engineer: Richard McKenzie
    Construction Contract Value: $425,977.00
    Construction Bid Price: $351,252.40
    Initial Construction Estimate: $381,450.00
    District: District 5

    Contracts (1) Progress
    # 36048 -- Construction Contract
    Falmouth - Shining Sea Bikeway Phase IIB Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/08/2004
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/09/2001
    Project Review Committee PRC Tabled 10/31/2001
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 11/30/2001
    Project Status Advertised 07/17/2004
    Project Management
    100% Design 100% Package Received 04/15/2003
    100% Design 100% Package Comments to DE 11/07/2003
    100% Design 100% Plans Approved 12/31/2003
    100% Design 100% Plans Complete 06/10/2004
    Final Design PS&E Received 09/05/2003
    Final Design PS&E to FAPRO 09/05/2003