PEABODY- BRIDGE REPLACEMENT, P-03-013, HOWLEY STREET OVER NORTH RIVER
The proposed project includes the demolition of the existing bridge that carries Howley Street over North River and the construction of a new one or two span bridge. The roadway and bridge approaches will remain in the existing footprint. The new bridge will consist of two travel lanes with shoulders, curb and sidewalk, and steel rail on both sides. Two lanes of traffic will be maintained during construction.
Location:
  • City of Peabody
  • Resident Engineer: Pamela Mamacos
    Construction Contract Value: $2,324,079.00
    Construction Bid Price: $1,894,852.08
    Initial Construction Estimate: $1,827,278.25
    District: District 4

    Contracts (4) Progress
    # 60139 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support servives to support the Bridge Preservation/Betterment Program. Final
    # 60283 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 79508 -- Construction Contract
    Bridge Replacement (P-03-013) (Concrete Box Culvert) - Howley Street over the North River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/22/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    Scope of Work
    A new scope of work and design contract is required for this bridge.
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/23/2001
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/21/2002
    Project Status Advertised 08/31/2013
    Project Management
    25% Design 25% Package Received 11/23/2004
    25% Design 25% Package Received 07/02/2012
    25% Design 25% Package Comments to DE 08/06/2012
    25% Design 25% Package Approved 12/12/2012
    25% Design Design Public Hearing 01/19/2005
    25% Design Design Public Hearing 01/09/2013
    25% Design 25% Plans Complete 12/12/2012
    75% Design 75% Package Received 03/22/2013
    Final Design PS&E Received 07/18/2013
    Consultant Contract Process Scope to DE 12/05/2001
    Consultant Contract Process NTP Issued 03/11/2002