Project Description:
SHREWSBURY- RESURFACING & RELATED WORK ON SECTIONS OF ROUTE 20, FROM SUNDERLAND ROAD WEST TO MILLBURY T.L.
This project will commence at Route 140 in Shrewsbury and continue in a westerly direction to Massasoit Road in Worcester, a distance of approximately 3.5 miles.
Location:
  • Town of Shrewsbury
  • Resident Engineer: Neil Raymond
    Construction Contract Value: $2,506,381.00
    Construction Bid Price: $2,240,910.00
    Initial Construction Estimate: $2,809,370.00
    District: District 3

    Contracts (1) Progress
    # 60860 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 20. (Re-Advertised) (ARRA Project) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/27/2009
    Contract Information
    Project Designer: In-House Boston
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/23/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Review Committee Letter 01/14/2002
    Project Status Advertised 06/13/2009
    Project Status Advertised 09/12/2009
    Project Management
    100% Design 100% Package Received 06/10/2009
    100% Design 100% Package Received 08/12/2009
    75% Design 75% Package Received 05/08/2009
    75% Design 75% Package Comments to DE 05/15/2009
    Final Design PS&E Received 06/10/2009
    Final Design PS&E to FAPRO 06/10/2009
    Final Design PS&E to FAPRO 09/09/2009
    Consultant Contract Process NTP Issued 02/02/2009