Project Description: |
STURBRIDGE- RESURFACING AND RELATED WORK ON ROUTE I-84 FROM CONNECTICUT S.L. TO ROUTE I-90
This project consists of resurfacing and related work (bridge deck repairs, guardrail replacement, drainage system cleaning and repairs, tree and brush removal along shoulders) I-84 from the Connecticut State Line easterly 7.0 miles to the Massachusetts Turnpike, I-90. All the interchanges are included in the work.
|
Location: |
|
Resident Engineer: | Paul Thompson |
Construction Contract Value: | $7,794,681.69 |
Construction Bid Price: | $6,615,722.92 |
Initial Construction Estimate: | $6,624,656.00 |
District: | District 3 |
Current Status: | Project 70% complete. Remaining work in 2005 to include paving the top course on the northbound barrell, landscaping and general project cleanup. (as of 09/07/2004) |
|