Project Description:
OXFORD- HIGHWAY RECONSTRUCTION INCLUDING INTERSECTION REALIGNMENT AND WIDENING, ROUTE 12 AT DEPOT ROAD
The proposed project consists of reconstructing the intersection of North Main Street (Route 12) at Depot Road, in the Town of Oxford. The work will include full depth reconstruction, raising the roadway profile to improve the sight distance for southbound and northbound traffic, new sidewalks, upgrading geometrics, drainage system improvements, traffic signs, pavement markings, new guardrail and landscaping.
Location:
  • Town of Oxford
  • Resident Engineer: David Windoloski
    Construction Contract Value: $933,232.95
    Construction Bid Price: $638,485.15
    Initial Construction Estimate: $532,833.50
    District: District 3

    Contracts (1) Progress
    # 44287 -- Construction Contract
    Oxford - Intersection Reconstruction and Related Work at Route 12 (North Main Street) and Depot Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/15/2006
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/22/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Status Advertised 09/17/2005
    Project Management
    100% Design 100% Package Received 04/11/2005
    100% Design 100% Package Comments to DE 05/16/2005
    25% Design 25% Package Received 01/22/2003
    25% Design 25% Package Comments to DE 03/08/2004
    25% Design Design Public Hearing 05/06/2004
    75% Design 75% Package Received 11/19/2004
    75% Design 75% Package Comments to DE 01/31/2005
    Final Design PS&E Received 07/07/2005
    Final Design PS&E to FAPRO 07/07/2005