FITCHBURG- RECONSTRUCTION OF NORTH STREET, FROM PEARL STREET TO ROSS STREET (PHASE III)
The project involves resurfacing, minor box widening, sidewalk reconstruction, minor drainage improvements, street lighting, streetscape trees and the signalization of the Peal Street intersection. The project length is 0.31 miles.
Location:
  • City of Fitchburg
  • Resident Engineer: Steven Miller
    Construction Contract Value: $1,775,680.70
    Construction Bid Price: $1,298,800.70
    Initial Construction Estimate: $1,250,089.00
    District: District 3

    Contracts (1) Progress
    # 54059 -- Construction Contract
    Fitchburg - Roadway Reconstruction and Related Work on a Section of North Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/19/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    Design Status
    MassHighway is presently awaiting the submission of the city's 25% design plans. The city anticipates submitting these plans by late Spring of 2005.
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/22/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/29/2005
    Project Status Advertised 08/25/2007
    Project Management
    100% Design 100% Package Received 06/28/2007
    100% Design 100% Package Comments to DE 07/31/2007
    25% Design 25% Package Received 07/02/2005
    25% Design 25% Package Comments to DE 01/06/2006
    25% Design Design Public Hearing 11/13/2006
    75% Design 75% Package Received 01/16/2007
    75% Design 75% Package Comments to DE 04/04/2007
    Consultant Contract Process Scope to DE 09/30/2003