LITTLETON- RECONSTRUCTION OF GOLDSMITH STREET, FROM ROUTE 2A/110 TO THE SHAKER LANE INTERSECTION
The proposed project consists of improvements to Goldsmith Street, from the intersection with Route 2A/110 to the intersection with Shaker Lane, a distance of approximately 1.45 miles. Sidewalk and landscaping improvements will also be provided.
Location:
  • Town of Littleton
  • Resident Engineer: Steven Miller
    Construction Contract Value: $3,774,487.68
    Construction Bid Price: $3,212,756.94
    Initial Construction Estimate: $4,013,117.00
    District: District 3

    Contracts (1) Progress
    # 57087 -- Construction Contract
    Littleton - Reconstruction of Goldsmith Street, Highway Reconstruction Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/10/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 10/31/2001
    Project Status Advertised 08/02/2008
    Project Management
    100% Design 100% Package Received 04/27/2006
    100% Design 100% Package Comments to DE 01/31/2007
    25% Design 25% Package Received 04/02/2002
    25% Design 25% Package Comments to DE 07/23/2002
    25% Design Design Public Hearing 01/15/2003
    75% Design 75% Package Received 03/26/2004
    75% Design 75% Package Comments to DE 01/03/2005
    Final Design PS&E Received 07/23/2008
    Final Design PS&E to FAPRO 07/29/2008