Project Description:
DEDHAM- BRIDGE REHABILITATION, D-05-005, AMES STREET OVER THE CHARLES RIVER
The proposed project consists of replacing the currently closed easterly sidewalk spans (built 1917) with a new replicated structure. The original masonry arches (built 1870) and concrete arches (built 1926) along the westerly side will be maintained and a new deck will span these historic arches. The bridge will be opened to vehicle traffic during construction and a foot-bridge will be constructed for pedestrians.
Location:
  • Town of Dedham
  • Resident Engineer: Eric Zilinsky
    Construction Contract Value: $8,783,582.00
    Construction Bid Price: $7,647,620.00
    Initial Construction Estimate: $6,501,180.00
    District: District 4

    Contracts (2) Progress
    # 55038 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57419 -- Construction Contract
    Dedham- Bridge Replacement (D-05-005), Ames Street over the Charles River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/17/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/25/2001
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/21/2002
    Project Status Advertised 09/13/2008
    Project Management
    100% Design 100% Package Received 11/03/2005
    100% Design 100% Package Comments to DE 03/03/2006
    25% Design 25% Package Received 10/06/2003
    25% Design 25% Package Comments to DE 06/27/2004
    25% Design Design Public Hearing 03/09/2004
    75% Design 75% Package Received 10/01/2004
    75% Design 75% Package Comments to DE 06/15/2005
    Final Design PS&E Received 09/15/2006
    Final Design PS&E to FAPRO 09/09/2008
    Consultant Contract Process NTP Issued 06/12/2004