SPRINGFIELD- LANDSCAPING ON COLUMBUS AVENUE (EAST & WEST) ALONG ROUTE I-91 RAMP RELOCATION
The work consists of the landscape improvements along the side slopes and embankments along I-91, from Broad Street to State Street; the design of an irrigation system; and sidewalk and landscaping improvements to Union Street, Broad Street and portions of State Street.
Location:
  • City of Springfield
  • Resident Engineer: Thomas Kozik
    Construction Contract Value: $1,355,658.00
    Construction Bid Price: $1,157,871.00
    Initial Construction Estimate: $1,301,856.50
    District: District 2

    Contracts (1) Progress
    # 62253 -- Construction Contract
    Streetscape Improvements along Sections of Hall of Fame and East Columbus Avenues. (ARRA Project) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/18/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 10/24/2001
    Project Review Committee PRC Approved 10/31/2001
    Project Review Committee Letter 11/29/2001
    Project Status Advertised 12/26/2009
    Project Management
    100% Design 100% Package Received 08/11/2009
    100% Design 100% Package Comments to DE 09/29/2009
    25% Design 25% Package Received 08/25/2003
    25% Design 25% Package Comments to DE 12/01/2003
    25% Design Design Public Hearing 10/07/2003
    75% Design 75% Package Received 08/22/2005
    75% Design 75% Package Comments to DE 11/18/2005
    Final Design PS&E Received 12/03/2009
    Final Design PS&E to FAPRO 12/17/2009