| Project Description: |
ADAMS- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE 116
The project will begin at the Adams/Cheshire town boundary (MM 66.3) and will end just north of Commonwealth Avenue (MM 67.8) for a project length of approximately 1.5 miles. MassHighway will resurface Route 116 and address some minor drainage issues as well as replace the sidewalks to conform with the Americans with Disabilities Act. A 300 foot long retaining wall at the north end of the project will be replaced.
|
| Location: |
|
| Design Responsibility: | In-House Boston |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Albert Li![]() |
| Estimated Total Contract Cost: | $2,002,690.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 1 |
| Current Status: | This project is in the preliminary design phase. |
|