Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
PITTSFIELD- BRIDGE REPLACEMENT, P-10-026, ELM STREET OVER THE EAST BRANCH OF HOUSATONIC RIVER
The purpose of this project is to replace the structurally deficient bridge and restore the lighting fixtures.
Location:
  • City of Pittsfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Project Manager: Courtney Sulerud
    Estimated Total Contract Cost: $2,335,822.50
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 1
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 05/31/2002 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/06/2001
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/20/2002
    Project Management
    Consultant Contract Process Scope to DE 12/18/2001
    Consultant Contract Process NTP Issued 05/31/2002