| Project Description: |
PITTSFIELD- BRIDGE REPLACEMENT, P-10-026, ELM STREET OVER THE EAST BRANCH OF HOUSATONIC RIVER
The purpose of this project is to replace the structurally deficient bridge and restore the lighting fixtures.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | Municipality |
| Project Manager: | Courtney Sulerud![]() |
| Estimated Total Contract Cost: | $2,335,822.50 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 1 |
| Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 05/31/2002 ) |
|