Project Description:
BARRE- BRIDGE REPLACEMENT, B-02-012, VERNON AVENUE OVER THE WARE RIVER
The work includes replacing the existing Vernon Avenue bridge (7.4 meters) over the Ware River with a wider bridge (10 meters). The bridge will be closed and a detour will be provided during construction.
Location:
  • Town of Barre
  • Resident Engineer: Stefan Toth
    Construction Contract Value: $3,667,929.00
    Construction Bid Price: $3,171,754.00
    Initial Construction Estimate: $3,897,512.79
    District: District 2

    Contracts (3) Progress
    # 53932 -- Construction Contract
    Barre - Bridge Replacement - (B-02-012) (Steel) Vernon Avenue over the Ware River Completed
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/07/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/15/2001
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/20/2002
    Project Status Advertised 09/08/2007
    Project Management
    100% Design 100% Package Received 01/11/2007
    100% Design 100% Package Comments to DE 08/06/2007
    25% Design 25% Package Received 12/04/2002
    25% Design Design Public Hearing 08/07/2003
    75% Design 75% Package Received 03/16/2004
    75% Design 75% Package Comments to DE 11/08/2004
    Final Design PS&E to FAPRO 09/05/2007
    Consultant Contract Process NTP Issued 02/15/2002