Project Description:
MONTEREY- BRIDGE REPLACEMENT, BR# M-29-002, RIVER ROAD OVER KONKAPOT RIVER
This bridge replacement project involves the replacement of the River Road Bridge over Konkapot River in the Town of Monterey. The project length is 180 feet. The project will include drainage improvements and incorporate safety improvements such as guardrail, signing, and pavement markings.
Location:
  • Town of Monterey
  • Resident Engineer: Joseph Mastroianni
    Construction Contract Value: $1,080,687.00
    Construction Bid Price: $964,534.00
    Initial Construction Estimate: $1,028,948.50
    District: District 1
    Current Status: Bridge is open to traffic. (as of 07/31/2007)
    Additional Info: The bridge will be closed during construction with a detour utilizing Gould Road, Curtis Road and Route 23. (as of 09/25/2006)

    Contracts (1) Progress
    # 44007 -- Construction Contract
    Monterey - River Road over Konkapot River (M-29-2) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/10/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Bridge is open to traffic.
    Additional Info
    The bridge will be closed during construction with a detour utilizing Gould Road, Curtis Road and Route 23.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/20/2001
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/20/2002
    Project Status Advertised 07/16/2005
    Project Management
    100% Design 100% Package Received 06/27/2005
    25% Design 25% Package Received 09/19/2002
    25% Design 25% Package Comments to DE 06/01/2003
    25% Design Design Public Hearing 08/05/2003
    75% Design 75% Package Received 02/17/2005
    75% Design 75% Package Comments to DE 03/28/2005
    Final Design PS&E Received 07/06/2005
    Final Design PS&E to FAPRO 07/06/2005