Project Description:
BRIDGEWATER- SIGNALIZATION & IMPROVEMENTS, ROUTE 18/28 (BEDFORD STREET) AT WINTER STREET
This project will enhance safety and improve efficiency by installing a new traffic signal at the intersection of Bedford Street (Routes 18/28) and Winter Street in Bridgewater. The existing geometry will be improved to provide a bicycle lane on Winter Street and an improved radius to better accommodate trucks. This project will include the installation of crosswalks with wheelchair ramps and pushbutton pedestrian signals on both Bedford Street and Winter Street. The traffic signals will include an emergency pre-emption detector to allow emergency vehicles priority access through the intersection.
Location:
  • Town of Bridgewater
  • Resident Engineer: Robert Fitzgerald
    Construction Contract Value: $932,068.40
    Construction Bid Price: $673,601.03
    Initial Construction Estimate: $867,740.00
    District: District 5

    Contracts (1) Progress
    # 52878 -- Construction Contract
    Bridgewater - Intersection Reconstruction Including signals at Route 18/28 (Bedford Street) and Winter Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/27/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/19/2001
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 06/10/2002
    Project Status Advertised 09/23/2006
    Project Management
    100% Design 100% Package Received 08/21/2006
    100% Design 100% Package Comments to DE 09/22/2006
    25% Design 25% Package Received 09/29/2004
    25% Design 25% Package Comments to DE 06/22/2005
    25% Design Design Public Hearing 09/27/2005
    75% Design 75% Package Received 03/24/2006
    75% Design 75% Package Comments to DE 05/12/2006
    Final Design PS&E Received 11/02/2006
    Final Design PS&E to FAPRO 09/19/2006