Project Description: |
ASHFIELD- BRIDGE REPLACEMENT, BR# A-13-010, ROUTE 116 (PLAINFIELD ROAD) OVER THE SWIFT RIVER
The work consists of demolishing the bridge and superstructure, partial removal of the existing abutments, construction of a new bridge and abutments and improvements to the roadway approaches.
|
Location: |
|
Resident Engineer: | Glenn Cellana |
Construction Contract Value: | $1,243,499.00 |
Construction Bid Price: | $1,028,636.00 |
Initial Construction Estimate: | $1,088,916.00 |
District: | District 1 |
Current Status: | Final inspection is being scheduled. (as of 05/16/2007) |
Additional Info: | There will be one lane traffic controlled by a traffic signal throughout the project. (as of 04/04/2006) |
|
Bridges
|
|
|
|
|