ASHFIELD- BRIDGE REPLACEMENT, BR# A-13-010, ROUTE 116 (PLAINFIELD ROAD) OVER THE SWIFT RIVER
The work consists of demolishing the bridge and superstructure, partial removal of the existing abutments, construction of a new bridge and abutments and improvements to the roadway approaches.
Location:
  • Town of Ashfield
  • Resident Engineer: Glenn Cellana
    Construction Contract Value: $1,243,499.00
    Construction Bid Price: $1,028,636.00
    Initial Construction Estimate: $1,088,916.00
    District: District 1
    Current Status: Final inspection is being scheduled. (as of 05/16/2007)
    Additional Info: There will be one lane traffic controlled by a traffic signal throughout the project. (as of 04/04/2006)

    Contracts (1) Progress
    # 43123 -- Construction Contract
    Ashfield - Route 116 (Plainfield Road) over the Swift River - Bridge Replacement (A-13-010) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/12/2005
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Final inspection is being scheduled.
    Additional Info
    There will be one lane traffic controlled by a traffic signal throughout the project.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/10/2001
    Project Review Committee PRC Approved 05/06/2002
    Project Status Advertised 07/02/2005
    Project Status Advertised 08/13/2005
    Project Management
    100% Design 100% Package Received 07/15/2004
    100% Design 100% Package Comments to DE 09/07/2004
    25% Design 25% Package Received 06/05/2002
    25% Design 25% Package Comments to DE 10/08/2002
    25% Design Design Public Hearing 05/06/2003
    75% Design 75% Package Received 11/26/2003
    75% Design 75% Package Comments to DE 02/09/2004
    Final Design PS&E Received 01/28/2005
    Final Design PS&E to FAPRO 03/08/2005