Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CHELMSFORD- TRAFFIC SIGNALS, ROUTE 4 AT PARKHURST AND DAVIS ROADS, ROUTE 4 AT DALTON STREET
This project will improve intersection safety and efficiency through installation of traffic signals on North Road (Route 4) at Parkhurst Road and at Davis Road.
Location:
  • Town of Chelmsford
  • Resident Engineer: Gregory Ramstine
    Construction Contract Value: $1,904,906.00
    Construction Bid Price: $1,656,642.50
    Initial Construction Estimate: $1,378,854.50
    District: District 4
    Current Status: Contractors work completed as of 11/2/2007. (as of 11/21/2007)

    Contracts (1) Progress
    # 45543 -- Construction Contract
    Chelmsford - Intersection Reconstruction 2 Locations- Rte 4@ Parkhurst/Davis Rd & Rte 4@ Dalton Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/05/2006
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contractors work completed as of 11/2/2007.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/20/2001
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/21/2002
    Project Status Advertised 09/30/2005
    Project Management
    100% Design 100% Package Received 07/08/2005
    100% Design 100% Package Comments to DE 08/29/2005
    25% Design 25% Package Received 01/16/2004
    25% Design 25% Package Comments to DE 06/04/2004
    25% Design Design Public Hearing 09/13/2004
    75% Design 75% Package Received 02/04/2005
    75% Design 75% Package Comments to DE 05/17/2005
    Final Design PS&E Received 07/29/2005
    Final Design PS&E to FAPRO 07/29/2005