Project Description:
ATHOL- ORANGE- BRIDGE REPLACEMENT, A-15-030=O-03-020, ROUTE 2 OVER LAKE ROHUNTA
The work includes the demolition and disposal of the existing bridge, and the construction of a new 53 foot single span bridge with similar span length as the existing. The work includes the modification of the existing substructure, and construction of the proposed superstructure, including the steel bridge railing, approach slab, highway guardrail transition, roadway approaches, and all related work. The work includes, but is not limited to, clearing, excavation, borrow, grading, highway guard, pavement markings, roadway pavement, drainage system, roadway embankment, riprap, and permanent and temporary traffic signs and traffic management devices. The bridge will be constructed in stages and traffic will be maintained on Route 2 during construction.
Location:
  • Town of Athol
  • Town of Orange
  • Resident Engineer: Ralph Romano
    Construction Contract Value: $1,919,394.00
    Construction Bid Price: $1,526,740.00
    Initial Construction Estimate: $1,284,113.60
    District: District 2

    Contracts (3) Progress
    # 30277 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 54992 -- Construction Contract
    Athol - Orange - Bridge Replacement (A-015-030=O-03-020) Rte 2 over Lake Rohunta Completed
    # 77872 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 07/10/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/11/2001
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 06/12/2002
    Project Status Advertised 08/25/2007
    Project Management
    100% Design 100% Package Received 10/18/2006
    100% Design 100% Package Comments to DE 11/21/2006
    25% Design 25% Package Received 02/26/2004
    25% Design 25% Package Comments to DE 07/13/2004
    25% Design Design Public Hearing 03/29/2005
    75% Design 75% Package Received 10/25/2005
    75% Design 75% Package Comments to DE 03/22/2006
    Final Design PS&E Received 11/28/2006
    Final Design PS&E to FAPRO 08/23/2007
    Consultant Contract Process Scope to DE 01/08/2002
    Consultant Contract Process NTP Issued 08/26/2002