Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
AMHERST- BRIDGE REPLACEMENT, BR# A-08-013, MEADOW STREET OVER SWAMP BROOK (EASTMAN BROOK)
The proposed project consists of the replacement of the Meadow Street Bridge over the Swamp Brook on the existing alignment with improvements to the approach roadway.
Location:
  • Town of Amherst
  • Resident Engineer: Joseph Gaudet Jr
    Construction Contract Value: $1,084,228.00
    Construction Bid Price: $976,162.00
    Initial Construction Estimate: $810,358.00
    District: District 2
    Current Status: Physical work complete (as of 06/11/2006)
    Additional Info: Bridge open to traffic (as of 05/10/2007)

    Contracts (1) Progress
    # 43663 -- Construction Contract
    amherst - meadow street over swamp brook Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/13/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Physical work complete
    Additional Info
    Bridge open to traffic
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/04/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/20/2002
    Project Status Advertised 08/13/2005
    Project Management
    100% Design 100% Package Received 02/10/2004
    100% Design 100% Package Comments to DE 05/06/2005
    25% Design 25% Package Received 04/12/2002
    25% Design 25% Package Comments to DE 06/10/2002
    25% Design Design Public Hearing 09/30/2002
    75% Design 75% Package Received 08/21/2003
    75% Design 75% Package Comments to DE 11/10/2003
    Final Design PS&E Received 07/06/2005
    Final Design PS&E to FAPRO 07/06/2005