ORANGE- BRIDGE REPLACEMENT, O-03-024, WEST RIVER STREET OVER ROUTE 2
The proposed project includes the demolition of the existing three span steel stringer bridge located on West River Street over State Route 2 and the construction of a single span steel stringer bridge. The proposed roadway width will be 33 feet with two 12 feet travel lanes and two 4 feet shoulders. A 5 foot sidewalk will be included on the structure. The bridge will be closed during construction. Traffic on State Route 2 wishing to use Exit 14 (West River Street, Lake Mattawa, Holtshire Road) will be routed to adjacent Route 2 Exits. Both eastbound and westbound shoulders on State Route 2 will be closed during construction
Location:
  • Town of Orange
  • Resident Engineer: Ralph Romano
    Construction Contract Value: $2,701,407.00
    Construction Bid Price: $2,383,006.95
    Initial Construction Estimate: $3,800,996.07
    District: District 2

    Contracts (2) Progress
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 60311 -- Construction Contract
    Bridge Replacement (O-03-024) (Steel) - West River Street over Route 2 (Mohawk Trail). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/08/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/17/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/31/2002
    Project Status Advertised 08/29/2009
    Project Management
    100% Design 100% Package Received 12/04/2008
    100% Design 100% Package Comments to DE 01/12/2009
    25% Design 25% Package Received 02/19/2003
    25% Design 25% Package Comments to DE 05/06/2003
    25% Design Design Public Hearing 02/25/2004
    75% Design 75% Package Received 03/13/2008
    75% Design 75% Package Comments to DE 05/21/2008
    Final Design PS&E Received 05/26/2009
    Final Design PS&E to FAPRO 07/02/2009
    Consultant Contract Process NTP Issued 07/14/2008