| Project Description: |
ATTLEBORO- BRIDGE PRESERVATION, A-16-042, I-95 (NB & SB) OVER WASHINGTON ST (US 1); BR# A-16-043, I-95 NB & SB OVER NEWPORT AVE (RTE 1A); BR# A-16-061 I-295 NB & SB OVER I-95.
The proposed project consists of cleaning and painting of three bridges on Route I-95, in the City of Attleboro. The work also involves patching the bridge decks, replacing joints, and upgrading bridge and safety railing.
|
| Location: |
|
| Resident Engineer: | Michael Giovanelli![]() |
| Construction Contract Value: | $4,629,221.00 |
| Construction Bid Price: | $3,842,635.22 |
| Initial Construction Estimate: | $4,102,401.00 |
| District: | District 5 |
|