ASHLAND- BRIDGE REPLACEMENT, A-14-002, ROUTE 135 (UNION STREET) OVER THE SUDBURY RIVER
The proposed project consists of replacing the existing Union Street (Route 135) bridge over the Sudbury River in its present location with minor improvements to the approach roadways. The bridge will be remain open during construction utilizing staged construction.
Location:
  • Town of Ashland
  • Resident Engineer: Michael Sholock
    Construction Contract Value: $2,284,285.00
    Construction Bid Price: $1,957,895.62
    Initial Construction Estimate: $2,439,232.00
    District: District 3

    Contracts (3) Progress
    # 57463 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 59590 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 65274 -- Construction Contract
    Bridge Replacement (A-14-002) (Concrete) – Route 135 (Union Street) over the Sudbury River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/14/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/25/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 06/10/2002
    Project Status Advertised 06/12/2010
    Project Management
    100% Design 100% Package Received 01/19/2010
    100% Design 100% Package Comments to DE 02/25/2010
    25% Design 25% Package Received 04/11/2008
    25% Design 25% Package Comments to DE 10/24/2008
    25% Design Design Public Hearing 04/21/2009
    75% Design 75% Package Received 08/26/2009
    75% Design 75% Package Comments to DE 11/10/2009
    Final Design PS&E Received 03/10/2010
    Final Design PS&E Received 04/27/2010
    Final Design PS&E to FAPRO 06/02/2010
    Consultant Contract Process Scope to DE 06/14/2004
    Consultant Contract Process NTP Issued 02/16/2005
    Consultant Contract Process Workhours Approved 02/02/2005