FALMOUTH- RECONSTRUCTION OF ROUTE 28 AT REINE'S CORNER
This project consists of safety improvement on a curve along Route 28 in East Falmouth locally known as Reine's Corner. The project is approximately 1800 feet long and consists of flattening the horizontal curve and improving the vertical alignment. The roadway work will be primarily full depth construction. Work also includes sidewalk construction and reconstruction and drainage upgrades. The location is the site of a number of fatalities over several years.
Location:
  • Town of Falmouth
  • Resident Engineer: Malcolm Lavalley
    Construction Contract Value: $1,442,250.00
    Construction Bid Price: $1,237,500.60
    Initial Construction Estimate: $1,866,355.00
    District: District 5

    Contracts (1) Progress
    # 61266 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Route 28 at Reine's Corner. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/15/2010
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/05/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 06/12/2002
    Project Status Advertised 09/19/2009
    Project Management
    100% Design 100% Package Received 12/09/2008
    100% Design 100% Package Comments to DE 12/29/2008
    25% Design 25% Package Received 11/27/2006
    25% Design Design Public Hearing 05/17/2007
    75% Design 75% Package Received 11/29/2006
    75% Design 75% Package Comments to DE 01/22/2007
    Final Design PS&E Received 09/04/2009
    Final Design PS&E to FAPRO 09/15/2009