| Project Description: |
DISTRICT 3- FABRICATION AND INSTALLATION OF OVERHEAD AND GROUND MOUNTED GUIDE SIGNS (5 SEPARATE CONTRACTS)
The purpose of this project is to ensure motorist safety and guidance along the State Highway System by providing new warning, regulatory, and guide signs. This is a sign maintenance project to replace signs that are worn and non-reflective and no longer meet present standards.
|
| Location: | |
| Resident Engineer: | Wallace Seaver![]() |
| Construction Contract Value: | $444,258.50 |
| Construction Bid Price: | $334,658.50 |
| Initial Construction Estimate: | $351,000.00 |
| District: | District 3 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
|||||||||||||||||