Project Description:
DISTRICT 4- FABRICATION AND INSTALLATION OF OVERHEAD AND GROUND MOUNTED GUIDE SIGNS (5 SEPARATE CONTRACTS)
The purpose of this project is to ensure motorist safety and guidance along the State Highway System by providing new warning, regulatory, and guide signs. This is a sign maintenance project to replace signs that are worn and non-reflective and no longer meet present standards.
Location:
Resident Engineer: Peter Gfatter
Construction Contract Value: $566,503.95
Construction Bid Price: $553,703.95
Initial Construction Estimate: $687,000.00
District: District 4
Current Status: Contract has ended. Completion date July 31, 2005. Final estimate is pending. (as of 09/20/2005)

Contracts (1) Progress
# 33074 -- Construction Contract
Fabrication and Installation of Overhead and Ground Mounted Guide Signs. (5 Separate Contracts) Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/04/2002
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contract has ended. Completion date July 31, 2005. Final estimate is pending.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/10/2002
    Project Status Advertised 03/30/2002
    Project Management