Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NEW BEDFORD- SIGNALIZATION & IMPROVEMENTS, KING'S HIGHWAY AND MOUNT PLEASANT STREET
This project will include the installation of traffic signals, new pavement markings and signs, wheelchair ramps and some widening to improve safety at the intersection of Kings Highway and Mount Pleasant Street. Traffic signals at this intersection will be coordinated with 3 adjacent intersections that are already signalized.
Location:
  • City of New Bedford
  • Resident Engineer: Alfredo Nunez
    Construction Contract Value: $697,930.53
    Construction Bid Price: $577,564.65
    Initial Construction Estimate: $659,320.60
    District: District 5

    Contracts (1) Progress
    # 51803 -- Construction Contract
    New Bedford -Traffic Signal Improvements and Related Work at Kings Highway / Jones Street and Mount Pleasant Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/18/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/11/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/28/2002
    Project Status Advertised 08/12/2006
    Project Management
    100% Design 100% Package Received 06/27/2006
    100% Design 100% Package Comments to DE 08/01/2006
    25% Design 25% Package Received 04/06/2004
    25% Design 25% Package Comments to DE 06/09/2004
    25% Design Design Public Hearing 11/22/2005
    75% Design 75% Package Received 09/21/2004
    75% Design 75% Package Comments to DE 08/26/2005
    Final Design PS&E Received 08/08/2006
    Final Design PS&E to FAPRO 08/08/2006
    Consultant Contract Process NTP Issued 09/16/2003