Project Description: |
NEW BEDFORD- SIGNALIZATION & IMPROVEMENTS, KING'S HIGHWAY AND MOUNT PLEASANT STREET
This project will include the installation of traffic signals, new pavement markings and signs, wheelchair ramps and some widening to improve safety at the intersection of Kings Highway and Mount Pleasant Street. Traffic signals at this intersection will be coordinated with 3 adjacent intersections that are already signalized.
|
Location: |
|
Resident Engineer: | Alfredo Nunez |
Construction Contract Value: | $697,930.53 |
Construction Bid Price: | $577,564.65 |
Initial Construction Estimate: | $659,320.60 |
District: | District 5 |
|