Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DIGHTON- TAUNTON- BRIDGE REPLACEMENT, D-08-013=T-01-025, OLD SOMERSET AVENUE OVER THE THREE MILE RIVER
The work under this project consists of replacing the town-owned and structurally-deficient Old Somerset Avenue bridge over the Three Mile River with a new bridge. The existing bridge will be removed and replaced with a pre-cast concrete arch bridge. The bridge roadway approaches will be reconstructed or cold-planed along with new guardrail, roadway drainage, and utility line relocation. The bridge will be closed during construction and traffic detoured.
Location:
  • Town of Dighton
  • City of Taunton
  • Resident Engineer: Rajat Gogoi
    Construction Contract Value: $1,358,127.00
    Construction Bid Price: $1,232,389.00
    Initial Construction Estimate: $1,329,336.35
    District: District 5

    Contracts (1) Progress
    # 58792 -- Construction Contract
    Bridge Replacemnt (D-08-013=T01-025) Old Somerset Avenue over the Three Mile River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/21/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/19/2002
    Project Review Committee PRC Approved 05/06/2002
    Project Review Committee Letter 05/21/2002
    Project Status Advertised 04/18/2009
    Project Management
    100% Design 100% Package Received 06/23/2008
    100% Design 100% Package Comments to DE 07/07/2008
    25% Design 25% Package Received 04/22/2002
    25% Design 25% Package Comments to DE 09/04/2002
    25% Design Design Public Hearing 11/06/2002
    75% Design 75% Package Received 03/11/2003
    75% Design 75% Package Comments to DE 06/11/2003
    Final Design PS&E Received 08/18/2008
    Final Design PS&E to FAPRO 04/14/2009
    Consultant Contract Process NTP Issued 03/07/2002